Liverpool Cemetery Roadworks
Modi was engaged to undertake critical road rehabilitation works at Liverpool Cemetery, addressing deteriorated pavement conditions across multiple key sections of the site. The project involved the complete reconstruction of subgrades, pavements, kerbs, and drainage infrastructure to ensure long-term functionality and improved access throughout the cemetery. What made this project particularly sensitive was its timing. All works had to be carefully completed within a strict one-month window — leading up to Father’s Day, one of the most emotionally significant days of the year for visitors. Our team worked with unwavering commitment to ensure zero disruption to cemetery operations during this period. Each phase was scheduled and delivered with precision, respect, and full awareness of the importance of the site and its visitors. All works were successfully completed ahead of time.
Project Overview
Modi was engaged to undertake critical road rehabilitation works at Liverpool Cemetery, addressing deteriorated pavement conditions across multiple key sections of the site. The project involved the complete reconstruction of subgrades, pavements, kerbs, and drainage infrastructure to ensure long-term functionality and improved access throughout the cemetery. What made this project particularly sensitive was its timing. All works had to be carefully completed within a strict one-month window — leading up to Father’s Day, one of the most emotionally significant days of the year for visitors. Our team worked with unwavering commitment to ensure zero disruption to cemetery operations during this period. Each phase was scheduled and delivered with precision, respect, and full awareness of the importance of the site and its visitors. All works were successfully completed ahead of time.
Scope of Works
- Removal and replacement of approximately 3,000m² of damaged pavement
- Excavation and reinstatement of subgrade with 200mm recycled DGB20
- Reconstruction of kerb and guttering with 25MPA concrete
- Asphalt resurfacing using AC10 hot mix @ 40mm thick
- Installation of 5 stormwater pits and approximately 250m of underground pipework
- Ag-line drainage installation along key sections
- Backfilling, compaction, and restoration of surrounding areas
- Temporary fencing and on-site safety controls maintained throughout